(Askeri) PROGRAM KIYMETLENDİRME VE İNCELEME TEKNİĞİ (HV.): Teşkilatlı herhangi bir çalışmanın incelenmesi ve kıymetlendirilmesiyle ilgili manajman tekniği. Bu teknik; yapılacak her iş unsurunun zaman, maliyet veya performansına değinen ve, başlangıçta planlanmış işi tamamlayacak üç parametreye ait tahminlerle birlikte, yapılan işlere ait bilgileri veren net işletme teorisine dayanır
Английский Язык - Английский Язык
Определение program and evaluation review technique в Английский Язык Английский Язык словарь
PERT is a project management technique for determining how much time a project needs before it is completed Each activity is assigned a best, worst, and most probable completion time estimate These estimates are used to determine the average completion time The average times are used to figure the critical path and the standard deviation of completion times for the entire project
(Ticaret) (PERT) A project management system that determines the project finish date by estimating best (shortest), worst (longest) and most likely duration times for activities on the critical path
A project management system that determines the project finish date by estimating best (shortest), worst (longest) and most likely duration times for activities on the critical path
A method for analyzing the tasks involved in completing a given project, estimating the time needed to complete each task, and identifying the minimum time needed to complete the total project
An event-oriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates PERT applies the critical path method to a weighted average duration estimate Also given as Program Evaluation Review Technique
An event-oriented network analysis technique used to estimate project duration when there is a high degree of uncer-tainty with the individual activity duration estimates PERT applies the critical path method to a weighted average duration estimate Also given as Program Evaluation and Review Technique
An event-oriented network analysis technique used to estimate program duration when there is uncertainty in the individual activity duration estimates PERT applies the critical path method using durations that are computed be a weighted average of optimistic, pessimistic, and most likely duration estimates PERT computes the standard deviation of the completion date from those of the path's activity durations Also known as the Method of Moments Analysis
An eventoriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates PERT applies the critical path method to a weighted average duration estimate Also given as Program Evaluation and Review Technique